Manufacturing Process Planning

At SOMADE we understand that keeping momentum on projects is an important key to success and leads to peace of mind for our clients.

On this project, we delivered 33,000 custom sets of figurines within 30 days of PO.

Here is a snapshot of this impressive timeline:
04/15 Received screen shots/images from client to match
04/20 Manufacturer completed clay molds for client approval
04/23 Client issues rush PO
04/23 Tooling starts for each character
04/24 E-Images are provided to confirm match of character
05/05 PMS colors
04/27 Box art/template provided to manufacturer
04/28 e-proofs for boxes provided
04/29 Final approvals given on all project aspects
04/30 Full production begins on all project aspects
05/05 Initial (first-off) minion set samples show production quality
05/19 SOMADE conducts QC inspection and certifies "PASS"
05/05 on production
05/21 Project shipped complete from China.

Lesson Learned: When you need it done right, count on
Somade to deliver.